|
I met with my team again
to review and discuss the associated costs for each phase. At the conclusion
of the meeting, we had agreed on $18,000 for supplies and 25% of the total
profits to cover their labor expenses. Meaning, I would purchase the
supplies upfront and the team would get paid a percentage of the profits
after the sale of the building for their labor.
|
Purchase Price: |
$240,000 |
ARV: |
$325,000 |
Repairs: |
$18,000 |
|
Closing Cost: |
$12,000 |
Mortgage Payments: |
$2,110 |
Potential Rental Income: |
$2,400 |
|
Potential Profit |
$48,670 |
Contractors Cost: |
$12,168 |
My ROI: |
$36,502 |
I was comfortable with the $36,502 profit that I had
calculated and decided there is no time like the present. So I submitted
my offer and it was accepted. I put 5% down and my loan consisted of
80/15, 3-year Interest Only, Combo Loan. Meaning, I had a $12,000 down
payment and financed the remaining $228,000 in 2 loans: 1) First mortgage
= $192,000 (80% of the purchase price) and a 2) Second mortgage = $36,000
(20% of the purchase price). I decided on an interest only, adjustable
rate mortgage (ARM) because it allowed for lower mortgage payments and my
plan was to fix and sell immediately, within three months to be exact. I
even had a contingency plan in place to rent the units in the event the
property didn’t sell within the three-month timeframe. Therefore, at
least the rents would cover the mortgage and I would not be losing money.
I closed in early November and I was officially an Investor.
So I went to Home Depot and opened a commercial
credit card account to cover the cost of the rehab supplies. I gave the
card to my team and I believed all was well. They had unlimited access to
the credit card and the list detailing the renovation work. It was divided
into four phases to be completed within a three-month timeframe. The
first of December arrived and I scheduled a meeting with my team to
discuss their progress. Unbeknowest to me, the demolition work was the
only thing they had completed. I was completely baffled, but I got over
it and together we revised the original plan in order the meet the
original completion date. I was ok with the results and they promised me
that they would be on it. This time, however, I planned to go check their
status on a weekly basis. At the end of the first week after our meeting,
I went to the property and surprise, they had not been there. Therefore,
the first week of the new plan was wasted. I called the team and was told
that they would be at the property the following week. Although I was
once again highly upset, I accepted it. After all they were not getting
paid until the project was complete.
The following week, I arrived at the property and the
work was in progress. Yet we still had a problem, they had replaced all
of the drywall throughout the building. The plan called for the basement
to be completely drywalled and for specific walls in Units 1 and 2 to be
replaced and not all the walls throughout the building. Now my repair
budget was off by $5000. In the process of re-drywalling, some of the oak
woodwork was damaged and had to be replaced. Oakwood trim is not cheap,
so that added another $1000 to my repair expense budget. We had just
begun and I was already $6000 over budget. The next week, while replacing
the electrical outlets, it was determined that some of the electrical
wiring needed to be replaced. An electrician was called in at an
additional cost of $1500. Then, because the vents and the furnaces were
left exposed during the demolition and drywall installation, the furnace
went out. I had to call a HVAC contractor to come out to clean and repair
the vents/furnaces for both units at $500 cost. Alright, at this time I’m
$8000 over budget and almost two months behind schedule.
February came and went, and my building was still
incomplete. Not only had the work not been completed, but they had
steered away from the defined phases. Everything was being done out of
sequence with no order and I decided enough was enough. Most of the major
work had been done in the 1st and 2nd floor units,
so I got involved in the painting and refinishing of the woodwork. It
took me about 3 weeks to finish both levels. The next week, I started
working on sanding and finishing the hardwood floors. Once again, I meet
with the team to discuss the progress and to hammer out the final stages
of the project and we came to an agreement of how to get the job done.
The next four weeks, the guys spent about one full week working on my
property. My bathrooms were incomplete, the basement and the garage
hadn’t been touched, the carpet needed to be laid, light fixtures hung,
and a couple of broken windows needed to replaced. These were things that
I couldn’t physically do and therefore I needed them to complete them. So
I scheduled another meeting and this time no one showed up. Can you
imagine how I felt? Another two weeks went by and I finally got a return
call from the team. I begged them to go ahead and finish the property.
Three weeks later the bathrooms were complete and the carpet was laid.
Another two months and the garage and the basement were finally complete.
Toward the middle of June, I was finally able to put the building on the
market for sale. It was not 100% complete, but enough was finished for
potential buyers to walk through and get a feel for how it would
eventually look.
Here we are in July and my building still isn’t
complete, therefore my contingency plan to rent it out is of no effect. I
consider myself lucky that I’m not in the hole yet, but my profit margin
has decreased considerably. I’ve spent $14,770 in mortgage payment,
$25,000 on repairs, totaling $39,770. I had initially allocated $24,300
to cover the mortgage payments and repairs, leaving me with a $15,470 loss
thus far. Some people say that experience is the best teacher and I can
honestly say that I learned some valuable lessons in this transaction that
may help you:
1)
Investing in real estate is an excellent way to change your
financial status and create wealth.
2)
Planning is vital to an investor’s success. However, the plan must
be followed and adjusted as necessary.
3)
Don’t underestimate the importance of good contractors.
Contractors should be properly screened. Get references and inquire about
their standard turnaround times. TIME IS MONEY!
4)
Hire someone to visit your property on a daily basis to ensure the
contractors are adhering to the plan.
5)
Don’t be afraid to get your hands dirty and take part in your
project.
6)
Use some precaution when working with family. Know what you are
getting into.
7)
INVEST WITH PASSION!
|